Summary
Beginning in July of 2022, the Office of Information Technology will begin the process of replacing all of the existing Extreme wired networking equipment in each building on campus with modern Aruba networking switches and routers. This process will bring the college network up-to-date with the latest routing, power-over-ethernet, network security, and traffic management technologies. This article will keep you updated on the progress.
Body
Overview
Beginning in July of 2022, the Office of Information Technology will begin the process of replacing all of the existing Extreme wired networking equipment in each building on campus with modern Aruba networking switches and routers. This process will bring the college network up-to-date with the latest routing, power-over-ethernet, network security, and traffic management technologies.
Status of the Project
This post will be constantly updated throughout the year with the tentatively scheduled events regarding the wired network upgrade initiative.
Check back from time to time to see the most current schedule, activities, and status.
Updated: 10/15/2023
Name |
Status |
Notes |
Allen House |
Complete |
2022-2023 |
Alumnae Hall |
Not yet started |
|
Blaney Hall |
Not yet started |
|
Butz Hall |
Not yet started |
|
Cressman Library |
Not yet started |
|
Curtis Hall |
Complete |
2023-2024 |
Data Center/Maintenance |
Partially Completed |
2022-2023 (Firewall, core router complete - switches still outstanding) |
FalconPlex |
Not yet started |
|
HBB |
Not yet started |
|
Lees Hall |
Complete |
2022-2023 |
Miller Building |
Not yet started |
|
Moore Hall |
Not yet started |
|
The Narrows |
Complete |
2023-2024 |
Oberkotter |
Complete |
2022-2023 |
Plant (Facilities/PS) |
Not yet started |
|
Rodale Aquatic Center |
Complete |
2022-2023 |
Security/Facilities/Mailroom |
Not yet started |
|
Steinbright Hall |
Not yet started |
|
Science Center |
Not yet started |
|
TCC |
Not yet started |
|