Summer 2022 Classroom Computer and A/V Replacement Schedule

Below is the list of classrooms that the Office of Information Technology is adding or upgrading the audio/visual system​s this summer.

This table will be updated with the most up-to-date information as it becomes available.  
Rooms, or portions of these rooms, may be unavailable between the Start and End dates. 

Current list is only the rooms, specific work and dates will be updated as soon as we are aware of them.

Note: some dates are contingent to the progress on construction/renovation projects outside of the Office of Information Technology.

Please check this list throughout the summer to see progress.

* Last Updated: 03/30/2022
** Information Updated

Building Room Work Being Done Starts Ends
HBB 6, 7, 8, 9 All A/V and Computers being replaced August 8th August 12th
Alumnae 202 A/V Late July  
Curtis 218 A/V Late July  
Curtis 253 A/V Late July  
         
         